SCHEDULE OF PAYMENTS

Payments are based on the construction progress of the property. You are required to pay progressive payments once the construction milestones are achieved and approved by the architect. The tables below represent the payment schedules for Residential Strata (Schedule H) and Landed properties (Schedule G).

  • Schedule H
  • Schedule G

For Strata Title

INSTALLMENT PAYABLE %
1. Immediately upon signing of the Agreement 10
2. Within thirty (30) working days after receipt by the Purchaser of the Developer's written notice of the completion of:-
a. the work below ground level of the said Building comprising the said Parcel including foundation of the said Building 10
b. the structural framework of the said Parcel 15
c. the walls of the said Parcel with door and window frames placed in position 10
d. the roofing, electrical wiring, plumbing (without fittings),gas piping(if any) and internal telephone trunking and cabling to the said Parcel 10
e. the internal and external finishes of the said Parcel including the wall finishes 10
f. the sewerage works serving the said Building 5
g. the drains serving the said Building 2.5
h. the roads serving the said Building 2.5
3. On the date the Purchaser takes vacant possession of the said Parcel with water and electricity supply ready for connection 17.5
4. On the date the Purchaser takes vacant possession of the said Parcel as in item 3 where the Developer has executed and delivered to the Purchaser or the Purchaser’s solicitor the instrument of transfer in favour of the Purchaser together with the original issue document of strata title to the said Parcel 2.5
5. On the date the Purchaser takes vacant possession of the said Parcel as in item 3 and to be held by the Developer's solicitor as stakeholder for payment to the Vendor as follows:
a. two point five per centum ( 2.5%) at the expiry of eight (8) months after the date the Purchaser takes vacant possession of the said Parcel; and 5
b. two point five per centum (2.5%) at the expiry of twenty-four (24) months after the date Purchaser takes vacant possession of the said Parcel.
TOTAL 100%